We shape the future of intermodal transport

 

Intermodal

We connect rail with road and sea all over Europe and beyond.

 

Connected

Our customers benefit from the power of a strong network.

 

Smart

We are the smart way of doing intermodal, with a wide range of services at a fair price.

 

Safe

Safety is our top priority: today and tomorrow.

 

Service

We run the extra-mile for our customers.

 

Quality

We fight for upgrading the performance of the rail system.

 

Agile

We listen, we cooperate, we develop, we deliver.

 

Emission-free

Together we make the green revolution happen.

Moving together 

 

The strategy of Hupac is based on strengths that have been built up over many years. The core elements are the demand-oriented development of a network for combined transport, independence from the railways and investments in own resources such as rail wagons, terminals and information technology.


Hupac’s target for the strategy period 2022-2026 is an annual volume increase of 7%. With a forecast economic growth of 2%, this will achieve a real shift of freight traffic from road to rail.


By 2026, Hupac aims to reach a traffic volume of 1.6 million road consignments, which corresponds to an increase of 40% compared to 2021. To achieve this goal, the Board of Directors has approved an investment programme of CHF 300 million.

Strategy 2026 in figures

 

Modal shift

1.6 million trucks transported by rail

 

Investment

CHF 300 million with focus on terminals, digitalisation, rail cars

 

Terminal capacity

1.3 million loading units in 7 new significant plants or expansions

 

Quality

90% punctuality by 2026

 

 

 

Modal shift: target 2026
Road consignments in the Hupac Group network

Competitive solutions for modal shift 

 

Stabilise the core business and exploit growth potentials – these are the guidelines of the Strategy 2026. The background is the upcoming expiry of operating subsidies for combined transport in Alpine transit through Switzerland. With the commissioning of AlpTransit, productivity advantages can be gradually exploited, such as more payload per locomotive, longer trains, shorter journey times. The core task for the 2022-2026 strategy period is to consistently integrate these factors into existing transport concepts.

 

In addition, the growth potentials arising in other areas of Europe should continue to be exploited. These include the axes of south-east, south-west and north-east Europe as well as new market segments such as maritime hinterland transport.

 

The optimisation of processes and the intelligent use of resources such as rail wagons and terminals are further fields of action. The central challenge is the efficient management of the network and the achievement of a quality level in line with requirements in a market that is characterised by capacity bottlenecks in certain phases as demand increases. Flexibility, digital intelligence and close cooperation with partners are the basic prerequisites for performance and customer satisfaction.

Strategic priorities

  • Quality leadership in European intermodal markets
  • Investments in market expansion and partnerships for modal shift
  • Digital transformation of our offerings and driving of sector standards
  • Attract talents and develop diversity for growth
  • Political advocacy to improve modal shift conditions and grow capacity.
Download

Contact

Final sprint for the construction of the Hupac Terminal Brwinów

New capacity for intermodal transport

Just a few more weeks to go – and then the construction of the new Hupac terminal in Poland will be completed. Diana Batko, head of the Hupac Terminal Brwinów subsidiary, is proud to give a preview.

 

The terminal is located in the immediate vicinity of the railway route from Warsaw towards Żyrardów and Skierniewice, some 15 km southwest of Warsaw. It extends on an area of 14 hectares and comprises a transhipment yard of 42,000 m2, four loading tracks with a minimum length of 750 m, office facilities and technical buildings.

 

Batko: “The terminal project is developed with a step-by-step approach. In a first phase, the loading units will be handled by reach-stackers. In a second phase, three more transhipment tracks will be added, as well as high performance gantry cranes”. The maximum capacity of the facility is 180,000 intermodal units per year.

 

Construction works will be completed by August 2022, while the operational start of the transhipment activity is planned for autumn 2022. The terminal will perform the transhipment of containers from road to rail and vice-versa for all types of intermodal units, including chemical products.