ERS Railways

ERS Railways is the Hupac Group branch for maritime inland transportation based in Germany. Founded in 1994, ERS has 30 years of expertise in intermodal services for maritime containers.

 

Our high-performance network for maritime container transport connects the seaports of Hamburg, Bremerhaven and Rotterdam with the most important economic centres in Germany. We move your containers - from the seaport by rail and onwards by road to the final destination. Fast, efficiently and eco-friendly.

 

Our Customer Service teams look after the entire range of container transport services. We take care of it - reliably and flexibly:

  • Container delivery: organisation of pre-carriage and on-carriage by truck
  • SOLAS services
  • Preparation of customs documents
  • Empty container positioning
  • Transport of dangerous goods by rail and road
  • Customised special services

 

For more information on timetables, services and offers, please visit www.ersrail.com

Get a quote

Contact

Works on the Rhine Valley line: all news about the replacement programme

 

From 8.4.22 to 24.4.22, extensive construction work take place on the Rhine Valley railway between Mannheim and Basel. During this period, the track capacity is greatly reduced due to various partial and full closures.

 

The replacement program


Together with DB Netze and our rail partners, we have drawn up a replacement program for around 70% of the regular trains. Just under half of these approximately 650 trains are scheduled via the Rhine Valley. All possible replacement capacities are used. The remaining volume is routed via the Gäubahn, Brenner and France. For 70% of the trains, we can offer the P400 profile.

 

Over the Easter holidays, the Rhine Valley line will be closed from 14.4.22, 23.00, until 18.4.22. Practically NO trains can run via the Rhine Valley. The already limited capacity will be further reduced to almost zero. The diversionary routes via Gäubahn, France and Brenner can accommodate just under 50% of the traffic.

 

Further measures


Extra trains are running between Busto and Basel to support transalpine traffic.

 

A task force is on duty 24/7 to coordinate possible events with the railways. Every opportunity to use any capacity that may become available is seized.

 

Preparations for week 16, when the train program will be ramped up again, are in full swing.


The implementation


14.4.2022 - As expected, not all trains of the closely timed diversionary service can circulate due to various traffic incidents. About 15% of the replacement program is cancelled due to operational disturbances.

Works on the Rhine Valley line: all news about the replacement programme

 

From 8.4.22 to 24.4.22, extensive construction work take place on the Rhine Valley railway between Mannheim and Basel. During this period, the track capacity is greatly reduced due to various partial and full closures.

 

The replacement program


Together with DB Netze and our rail partners, we have drawn up a replacement program for around 70% of the regular trains. Just under half of these approximately 650 trains are scheduled via the Rhine Valley. All possible replacement capacities are used. The remaining volume is routed via the Gäubahn, Brenner and France. For 70% of the trains, we can offer the P400 profile.

 

Over the Easter holidays, the Rhine Valley line will be closed from 14.4.22, 23.00, until 18.4.22. Practically NO trains can run via the Rhine Valley. The already limited capacity will be further reduced to almost zero. The diversionary routes via Gäubahn, France and Brenner can accommodate just under 50% of the traffic.

 

Further measures


Extra trains are running between Busto and Basel to support transalpine traffic.

 

A task force is on duty 24/7 to coordinate possible events with the railways. Every opportunity to use any capacity that may become available is seized.

 

Preparations for week 16, when the train program will be ramped up again, are in full swing.


The implementation


14.4.2022 - As expected, not all trains of the closely timed diversionary service can circulate due to various traffic incidents. About 15% of the replacement program is cancelled due to operational disturbances.