Milano Smistamento
Commissioner Terminal AlpTransit Srl (TerAlp) (Mercitalia Logistics – Gruppo FS Italiane, Hupac Ltd)
Project Construction and management of intermodal terminal on existing railway area
Surface 240,000 m2
Stacking lanes 10
Gantry cranes

Phase 1: 3

Phase 2: 6

Transhipment tracks 10 x 750 m
Stationing tracks 5 x 750 m 
Services

Parking areas for semi-trailers

Operating offices

Spare parts/short repair and maintenance warehouse

Max. capacity

Phase 1: 11 train pairs per day

(195,000 loading units/year)

Phase 2: 22 train pairs per day

(395,000 loading units/year)

Complementary works Mitigation and environmental compensation measures
Start-up

Phase 1: 2026

Milano Smistamento
Commissioner Terminal AlpTransit Srl (TerAlp) (Mercitalia Logistics – Gruppo FS Italiane, Hupac Ltd)
Project Construction and management of intermodal terminal on existing railway area
Surface 240,000 m2
Stacking lanes 10
Gantry cranes

Phase 1: 3

Phase 2: 6

Transhipment tracks 10 x 750 m
Stationing tracks 5 x 750 m 
Services

Parking areas for semi-trailers

Operating offices

Spare parts/short repair and maintenance warehouse

Max. capacity

Phase 1: 11 train pairs per day

(195,000 loading units/year)

Phase 2: 22 train pairs per day

(395,000 loading units/year)

Complementary works Mitigation and environmental compensation measures
Start-up

Phase 1: 2026

Get a quote

Contact

Milano Smistamento
Commissioner Terminal AlpTransit Srl (TerAlp) (Mercitalia Logistics – Gruppo FS Italiane, Hupac Ltd)
Project Construction and management of intermodal terminal on existing railway area
Surface 240,000 m2
Stacking lanes 10
Gantry cranes

Phase 1: 3

Phase 2: 6

Transhipment tracks 10 x 750 m
Stationing tracks 5 x 750 m 
Services

Parking areas for semi-trailers

Operating offices

Spare parts/short repair and maintenance warehouse

Max. capacity

Phase 1: 11 train pairs per day

(195,000 loading units/year)

Phase 2: 22 train pairs per day

(395,000 loading units/year)

Complementary works Mitigation and environmental compensation measures
Start-up

Phase 1: 2026

Single point of contact