Shuttle Net

Our services: resources, solutions, expertise

Reliable, flexible, and ready to go - across Europe.

Integrated network

with 130+ daily trains connecting major European corridors.

Efficient terminals

owned or co-managed, at key hubs like north Italy, Antwerp, Rotterdam, Duisburg, Cologne, Ludwigshafen, Singen, Vienna and Warsaw/Brwinów.

Modern fleet

of over 8,300 rail platforms for maximum flexibility and independence.

 

Expert teams

in 10 countries providing tailored, hands-on customer service.

 

Selected rail partners

best-in-class in their region, ensuring reliable traction.

 

Contingency-ready

with reserve trains, stand-by drivers, and 24/7 traffic control.

 

Smart digital tools

for booking, tracking, planning, and real-time updates.

 

Technical support

to ensure full compatibility with intermodal standards.

Get a quote

Contact

Peter
Dannewitz
Sales Director
Hupac Intermodal SA
Viale R. Manzoni 6
CH-6830 Chiasso
+41 58 8558155
pdannewitz@hupac.com
Alessandro
Valenti
Deputy CEO Hupac Intermodal Ltd |
Director Shuttle Net Transalpine
Corridor
Hupac Intermodal SA
Viale R. Manzoni 6
CH-6830 Chiasso
+41 58 8558100
avalenti@hupac.com
Intermodal corridor NEAT 2020: Achieving the greatest benefit with modest means

Position paper

The opening of the Gotthard base tunnel in 2017 and of the Ceneri base tunnel in 2019 are supposed to make goods transportation more efficient and to promote modal shift. However, the question of the access lines is still without answer. The existing lines present several limitation which strongly affect the performance of the whole corridor. Because of funding shortfalls the construction of new infrastructures is not to be expected in any time soon.

 

NEAT flat railway: small, affordable expansion steps

Hupac supports a pragmatic, progressive adjustment of the existing infrastructure so that the advantages of the flat railway can be exploited as soon as the Gotthard base tunnel is opened. The existing access lines can be expanded step by step as part of a transnational corridor concept encompassing the entire Rotterdam-Genoa.

 

Increasing the productivity of rail freight transport

Long and heavy trains make the best of the system advantages of rail transportation. The productivity of the railways must be increased, also in order to offset the reduction in operating subsidies. This requires infrastructural adjustments on the 130 years old Gotthard line according to the existing European directives.

 

4-meter-profile for the modal shift of modern semi-trailers

In the last 20 years the rate of semi-trailers in road transit via Switzerland has doubled and now amounts to 60% of all heavy vehicles. In order to shift this important segment to rail, the transit route has to be upgraded to rail profile P400.

 

 

Intermodal corridor via Gotthard and Simplon – the required measures

  • Train lengths 750 m, train weights 2,000 t: essential for the productivity and competitiveness of rail
  • 4-metre P400 profile as per international UIC standard for main transport routes: essential for shifting the important segment of high-volume transport
  • Piattaforma Luino and Simplon Phase II: expansion to train lengths of up to 750 metres; implementation on schedule
  • Priority for the intermodal corridor via Luino and Domodossola, which serves the existing Busto Arsizio and Novara terminals and handles over 60% of intermodal transport
  • Terminals east of Milan for the new Seregno-Bergamo line with a capacity of 30 train pairs per day
  • No funding of the intermodal corridor at the expense of operating subsidies: risk of reverse shift!
Renzo
Capanni
Director Company Shuttle & Shuttle
Net East Europe
Hupac Intermodal AG
Bruggerstrasse 37
CH-5400 Baden
+41 58 8558080
rcapanni@hupac.com
Intermodal corridor NEAT 2020: Achieving the greatest benefit with modest means

Position paper

The opening of the Gotthard base tunnel in 2017 and of the Ceneri base tunnel in 2019 are supposed to make goods transportation more efficient and to promote modal shift. However, the question of the access lines is still without answer. The existing lines present several limitation which strongly affect the performance of the whole corridor. Because of funding shortfalls the construction of new infrastructures is not to be expected in any time soon.

 

NEAT flat railway: small, affordable expansion steps

Hupac supports a pragmatic, progressive adjustment of the existing infrastructure so that the advantages of the flat railway can be exploited as soon as the Gotthard base tunnel is opened. The existing access lines can be expanded step by step as part of a transnational corridor concept encompassing the entire Rotterdam-Genoa.

 

Increasing the productivity of rail freight transport

Long and heavy trains make the best of the system advantages of rail transportation. The productivity of the railways must be increased, also in order to offset the reduction in operating subsidies. This requires infrastructural adjustments on the 130 years old Gotthard line according to the existing European directives.

 

4-meter-profile for the modal shift of modern semi-trailers

In the last 20 years the rate of semi-trailers in road transit via Switzerland has doubled and now amounts to 60% of all heavy vehicles. In order to shift this important segment to rail, the transit route has to be upgraded to rail profile P400.

 

 

Intermodal corridor via Gotthard and Simplon – the required measures

  • Train lengths 750 m, train weights 2,000 t: essential for the productivity and competitiveness of rail
  • 4-metre P400 profile as per international UIC standard for main transport routes: essential for shifting the important segment of high-volume transport
  • Piattaforma Luino and Simplon Phase II: expansion to train lengths of up to 750 metres; implementation on schedule
  • Priority for the intermodal corridor via Luino and Domodossola, which serves the existing Busto Arsizio and Novara terminals and handles over 60% of intermodal transport
  • Terminals east of Milan for the new Seregno-Bergamo line with a capacity of 30 train pairs per day
  • No funding of the intermodal corridor at the expense of operating subsidies: risk of reverse shift!