Maritime Logistics

Customer driven rail solutions

ERS Railways is the Hupac Group branch for maritime inland transportation based in Germany. Founded in 1994, ERS has 30 years of expertise in intermodal services for maritime containers.

 

Intermodal network

Our high-performance network for maritime container transport connects the seaports of Hamburg, Bremerhaven and Rotterdam with the most important economic centres in Germany. We move your containers – from the seaport by rail and onwards by road to the final destination. Fast, efficiently and eco-friendly.

 

With 30 years of experience in the field of intermodal services, we serve the terminals in Nuremberg, Munich, Augsburg, Regensburg, Ulm, Kornwestheim, Frankfurt and Mannheim as well as the border areas to the Czech Republic, Austria, France and Switzerland via combined transport.

 

Continental network of Hupac

In addition, ERS Railways offers the possibility of using the continental network of Hupac Intermodal for maritime volumes, allowing our customers to benefit from our full-service container handling on these routes as well. Furthermore, Hupac provides a pan-European network of container terminals that we can use.

 

Full-service container transport

Our Customer Service teams look after the entire range of container transport services. We take care of it – reliably and flexibly.

  • Container delivery: organisation of pre-carriage and on-carriage by truck
  • SOLAS services
  • Preparation of customs documents
  • Empty container positioning
  • Transport of dangerous goods by rail and road
  • Customised special services

 

An exclusive access to rail resources

Our strategic alignment with boxXpress as a private rail company and a jointly operated train network expands the spectrum for intermodal seaport-hinterland transport. As a shareholder of boxXpress, we get the best out of the market – and make optimal use of the available resources.

  • 37 Vectron locomotives for high sustainability value
  • 1000 container wagons Sggns(s) 80' with ideal loading weight
  • Professional train running control
  • Active CO2e management by ERS Railways

Get a quote

Download

Contact

Construction sites in August 2024: Hupac secures capacity thanks to diesel shuttle via France

What do you do when Europe's most important rail freight axis is closed for weeks and only a fraction of the capacity is available on alternative routes? The closure of the Rhine Valley line near Rastatt from 9 to 30 August 2024 was announced well in advance. The severe restrictions for diversionary traffic on the Gäubahn line between Stuttgart and Singen were also known: too few train paths per day, reduced profile of maximum P386.

 

Together with DB InfraGO and SNCF Réseau, SBB Cargo International and Captrain France, Hupac developed an innovative diversion concept via France, thus doubling the capacity for freight trains. What's more: "We can continue to offer our customers transport services with the standard P400 profile," stresses Alessandro Valenti, Director Shuttle Net at Hupac Intermodal.

 

How does the "diesel shuttle" work? Diesel locomotives are placed in front of the trains between Offenburg and Wörth in order to be able to use the route via France, which is not fully electrified. Eleven diesel locomotives and 80 specially trained drivers are used in double crews: a German-speaking and a French-speaking colleague share the cab to ensure communication with the national control centres.

 

The shuttle service is available to all freight trains on the corridor. The trains run according to a regular timetable, but on a FIFO (first in first out) basis to avoid wasting scarce capacity. "A pioneering project, made possible thanks to international cooperation across the industry. A project of which the entire sector can be proud", says Hupac CEO Michail Stahlhut. "Thanks to this initiative, we will be able to cover 80% of the transport demand in August and thus significantly support the industrial supply - despite the complete closure of the main European transport axis for several weeks".

 

From an operational point of view, the complex construction situation poses a major challenge. Valenti: "Our control centre is in contact with the railways and terminals around the clock in order to manage disruptions and irregularities in the best possible way."

 

The Hupac Intermodal customer teams are available for information on the updated timetable and for bookings.

Construction sites in August 2024: Hupac secures capacity thanks to diesel shuttle via France

What do you do when Europe's most important rail freight axis is closed for weeks and only a fraction of the capacity is available on alternative routes? The closure of the Rhine Valley line near Rastatt from 9 to 30 August 2024 was announced well in advance. The severe restrictions for diversionary traffic on the Gäubahn line between Stuttgart and Singen were also known: too few train paths per day, reduced profile of maximum P386.

 

Together with DB InfraGO and SNCF Réseau, SBB Cargo International and Captrain France, Hupac developed an innovative diversion concept via France, thus doubling the capacity for freight trains. What's more: "We can continue to offer our customers transport services with the standard P400 profile," stresses Alessandro Valenti, Director Shuttle Net at Hupac Intermodal.

 

How does the "diesel shuttle" work? Diesel locomotives are placed in front of the trains between Offenburg and Wörth in order to be able to use the route via France, which is not fully electrified. Eleven diesel locomotives and 80 specially trained drivers are used in double crews: a German-speaking and a French-speaking colleague share the cab to ensure communication with the national control centres.

 

The shuttle service is available to all freight trains on the corridor. The trains run according to a regular timetable, but on a FIFO (first in first out) basis to avoid wasting scarce capacity. "A pioneering project, made possible thanks to international cooperation across the industry. A project of which the entire sector can be proud", says Hupac CEO Michail Stahlhut. "Thanks to this initiative, we will be able to cover 80% of the transport demand in August and thus significantly support the industrial supply - despite the complete closure of the main European transport axis for several weeks".

 

From an operational point of view, the complex construction situation poses a major challenge. Valenti: "Our control centre is in contact with the railways and terminals around the clock in order to manage disruptions and irregularities in the best possible way."

 

The Hupac Intermodal customer teams are available for information on the updated timetable and for bookings.